c)
Tighten Mid and End-Clamps to hold module in place - do not fully torque
d)
Repeat steps 1-4 as required for remaining modules
e)
Torque clamps to 12 ft-lbs (16.3 N-m)
9.7.
Wire Management
Various Wire Management methods can be combined
9.7.1.
Cable Raceway
i.
Hang the Cable Raceway segment on the bottom edge of the side channel of the
rail
ii.
Lay cables into Cable Raceway segment. Rotate Raceway segment until it snaps
into top edge of side channel of rail
9.7.2.
Lock-On Cable Tie
i.
Place on rail where needed; approximately 1 x Cable Tie for every 1 foot of rail
ii.
Wrap Cable Tie around cables and fasten tightly