background image

 

CENTAURI ENERGY SERVER 

 

 

User Manual - Model 30-2017/12/18-VERSION 1.0 

 

20                                                                       

 

 

4.

 

Connect  the  protective  grounding  cables  and  other  necessary  grounding  cables  to 
the  connectors  of  the  ground  lines  at  the  bottom  of  the  Server’s  power  supply 
equipment. 

 

5.

 

Select  one  of  the  following  two  steps  bases  on  the  installation  types  to  mark  out 
and connect the input cables. 

 

6.

 

Connect the “R, S, T and N” ports of the BYP  INPUT (bypass input) terminal board to 
the  corresponding  with  the  “R,  S,  T  and  N”  ports  of  the  external  BYP  INPUT  power 
switch or breaker with the qualified connecting cables in the correct phase sequence 
and then fasten them. 

 

7.

 

Connect the “R, S, T and N” ports of the AC  INPUT (rectifier input) terminal board to 
the  corresponding  with  the  “R,  S,  T  and  N”  ports  of  the  external  BYP  INPUT  power 
switch or breaker with the qualified connecting cables in the correct phase sequence 
and then fasten them. 

 

8.

 

Connect  the  “R,  S,  T  and  N”  ports  of  the  AC  OUTPUT  (output)  terminal  board  to  the 
corresponding with the “R, S, T and N” ports of the external output distribution box with the 
qualified connecting cables in the correct phase sequence and then fasten them. 

 

9.

 

Connect  "battery  +”  and  “battery  -"  ports  of  the  Server  to  the  output  "+”  and  “-" 
poles of the battery box (pack) with the qualified connecting cables. 

 

10.

 

Connect  "PV  INPUT1#—4#  +”  and  “PV  INPUT1#—4#  -"  poles  of  the  Server  to  the  " 
” and “output -" poles of the corresponding PV combiner boxes of PV1 # - PV4# 
with the qualified connecting cables; Besides the electrode and the grounding terminal 
cannot be shared among the different groups. 

 

11.

 

Insert one end of the temperature sensor of the battery pack freely supplied with the 
device into battery. TEMP, with the other end stretched into the center of the battery 
box (pack) close to the battery along the battery line (option). 

 

12.

 

Confirm  that  all  switches  of  the  Server™  are  completely  shut  down  and  the  external 
switches  of  "rectifier  power  supply,  the  bypass  power  supply  and  the  battery  box 
(pack)" are switched on, and then use the multimeter to test and make sure that the 
voltage  and  polarity  of  the  system  should  comply  with  the  relevant  requirements  of 
the system rated voltage. 

 

13.

 

Install all protective cover plates in place. 

 

2.10 

Communication Interface 

 

 

This  system  is  equipped  with  RS485  and  RS232  interfaces  directly  serving  as  the 
interface  of  the  background  monitoring  software  to  provide  the  serial  data.  When 
the customers want to use it, they only need to connect the USB freely supplied with 
the device to the communication interface module (RS485 communication lines are 
optional) directly.

 

The system is provided with the preset "SNMP" card port (SNMP card for option) 
to facilitate the users to realize the remote monitoring (option).

 

2.11

 

Signal Interface 

 

 

The  control  signal  input  interface  refers  to  the  2Pin  interface,  therefore  the 
corresponding order can be conducted when in short circuit, as shown figure 
6.

 

 

 

 

Summary of Contents for 30-2012

Page 1: ...CENTAURI ENERGY SERVER User Manual Model 30 2017 12 18 VERSION 1 0...

Page 2: ...uttons 10 1 5 2 1 Description of Selection Button Functions 10 1 5 2 2 Description of Function Buttons 11 1 5 3 Introduction to Input Breaker 11 1 5 4 Introduction to Line Bank 12 1 5 5 Description of...

Page 3: ...ng 24 3 5 1 3 Power On Setting 25 3 5 1 4 Other Settings 25 3 5 2 User Setup 25 3 5 2 1 MPPT Setup 25 3 5 2 2 INV Setup 25 3 5 2 3 Off Peak Setup 25 3 5 2 4 Protocol Setup 26 3 5 2 5 Language Selectio...

Page 4: ...CENTAURI ENERGY SERVER User Manual Model 30 2017 12 18 VERSION 1 0 4 5 2 2 MPPT Warning Information 32 6 Attachment 33 6 1 Option 33 6 2 System Standard Accessories 33...

Page 5: ...nance and repair of the Server which can be performed only by authorized technicians o This system is provided with multiple PV inputs therefore it should be connected with the independent loop withou...

Page 6: ...cy even in the cases of a sudden change of AC input voltage and AC frequency over under voltage 1 2 Denomination GF 60K 360V 380V 3 3 Description of System Input output Three IN and Three OUT 380V vol...

Page 7: ...real time alarm information with 10 000 history alarm records for user query to provide reliable basis for fault diagnosis o The user can perform various operating commands through the touch screen in...

Page 8: ...nt power Parallel Active power KW Pout Active power machine Single machine When the Server is set as the single parameters system without parallel machine it only includes the load itself machine data...

Page 9: ...meters Battery self check and Press this button to set battery test or terminate the test maintenance History button Press this button to view the history of the Server system Skip button Press this b...

Page 10: ...le 3 System LED and Alarm 1 1 5 1 4 STATUS System Warning LED and Warning LED The red light is The green light is OFF Green light is normally on normally on normally on BYP bypass power Input voltage...

Page 11: ...ystem alarm is activated by pressing this button again FAULT CLEAR Clear the system Press this button to clear executed abnormal protection fault command the system will restart and run EPO Emergency...

Page 12: ...is BAT TEMP temperature Sensing used for the charge compensation BAT TEST Battery self Check The system performs the battery test The system boots in the standby mode by INV ON System ON pressing thi...

Page 13: ...pack voltage 360Vdc The number of ESDs 12V 2V 30 180 Working mode The PV and AC are complementary to PV and AC Maximum voltage 0 V 750Vdc range Voc Best working voltage 450 550Vdc Vmp Maximum 98 conv...

Page 14: ...es to bypass Automatically returns to Server when load is restored to normal 110 125 After10mins switches to bypass Automatically returns to Server when load is restored to normal Overload 125 150 Aft...

Page 15: ...ncy stop Communication Computer RS232 RS485 and SNMP Option monitoring port interface Dry contact output Bypass input fault rectifier input fault system fault system 12Vdc 250Vac 1A alarm battery low...

Page 16: ...oltage at the battery terminal will be more than 360 VDC which possesses the risk of fatal danger Please take off rings bracelets watches and other metal articles The tools with insulated handle s mus...

Page 17: ...chematic Diagram of System Installation 1 The altitude is less than 1000 meters otherwise the derating of Server should be used 2 In the environment the bearing capacity should be greater than the equ...

Page 18: ...ernal power supply should be more than 1 5 times of the equipment s rated power and the rated current of the power circuit breaker supply nearby the supply equipment should be more than 1 2 times not...

Page 19: ...ables should be around 2 10 meters Longer cable lengths lead to low voltage and therefore cross section area of the corresponding cable should be increased Rated Standards 10 20 30 40 50 60 Capacity K...

Page 20: ...he output and output poles of the corresponding PV combiner boxes of PV1 PV4 with the qualified connecting cables Besides the electrode and the grounding terminal cannot be shared among the different...

Page 21: ...ion involved in the operation steps and LED display are shown in the Product Profile Note 2 Before conducting any operation step described in this chapter please carefully read the instructions to avo...

Page 22: ...f the touch screen Touch operation Click the button OFF button and OK button in turn the system will switch off the machine 2 Turn off the output switch 3 Switch off the switches of PV 1 PV 4 in turn...

Page 23: ...bypass power supply through the maintenance bypass switch by conducting the following steps 1 After the bypass parameters is detected and confirmed being normal please click button on the main interf...

Page 24: ...tenance work and the load is powered up by the Server instead of the bypass system 3 5 System Setup Click button to enter the system setup interface 3 5 1 Advanced Setup Click the Advanced Setup butto...

Page 25: ...etup Operation method Click the User Setup button and input the password to enter the corresponding setting interface The user setting operation can only be done by the user 3 5 2 1 MPPT Setup MPPT se...

Page 26: ...e can be displayed in the following two formats 1 Year month day 2 month day year 3 5 2 8 User Password Control Password The system will provide the password protection to limit the operator for some...

Page 27: ...eater than the load power and AC fails the PV power will support the load at first and the extra power will be used to charge the battery Fig 10 AC Abnormal Mode 1 2 When the PV power is less than the...

Page 28: ...time the rectifier charge function will recover to charge the battery Fig 12 Mode 1 for Off peak Electricity Consumption 2 Off peak of electricity consumption After the off peak electricity consumptio...

Page 29: ...f input output and the battery are connected firmly and whether the insulation layer of the cables is in good condition 5 Ensure that the product should not be affected with dampness 6 Start up operat...

Page 30: ...down duo to too low voltage of busbar The voltage of battery discharge and busbar is lower than minimum set value The system won t automatically boot until the AC recovers or the PV is sufficient and...

Page 31: ...d itself is in Output in short circuit more than 5 times of the rated normal state and then press FAULT value within 100ms namely CLEAR button for recovery short circuit protection Press the red butto...

Page 32: ...rature of the module is Please ask the local caused by the fan fault authorized technician for service The transient The system automatic BUS overvoltage loading unloading causes the adjustment recove...

Page 33: ...e and start the charging function Table 14 MPPT Warning Information 6 Attachment 6 1 Option Harmonic suppression filter SNMP card Can sense remote wireless communication Parallel accessories Parallel...

Page 34: ...rmation The use of any such information will be entirely at the user s risk c can change the contents of the user manual without prior notice and at its sole discretion The information contained in th...