Installation Note N5222-90129 49
Installation Procedure for the Upgrade
Step 31. Verify the PNA Analyzer Program is Running with the Correct
Options
1.
Start the Network Analyzer program.
2.
Once the Network Analyzer program is running:
—
Press
Help
>
About NA
and verify that Option 401 is listed in the
PNA application.
3.
After successful installation of all upgrades, some features require some
adjustments to ensure the instrument meets its specified performance.
Refer to the following Web site:
http://na.support.keysight.com/pna
Step 34. Perform Post-Upgrade Adjustments and Calibration
Adjustments
The following adjustments must be made due to the hardware changes of the
analyzer.
— EE default Adjustment
— synthesizer bandwidth Adjustment (only run if the EE default adjustment is
insufficient)
— Source Adjustment
— IF Gain Adjustment
— Receiver Characterization
— Receiver Adjustment
— IF Response Adjustment (Option S93090xB, S93093B, or S93094B Only)
These adjustments are described in the PNA Service Guide and in the PNA
If the option is still not enabled or if your old option(s) have been removed,
contact Keysight Technologies. Refer to
.
IMPORTANT!
The 10 MHz reference crystal oscillator is the most accurate after running
for three hours. The 10 MHz Frequency Reference Adjustment can be run
after the PNA has warmed up for 90 minutes, and the other adjustments
can be completed in the order presented, but then the 10 MHz Frequency
Reference Adjustment should be repeated after the PNA has been able to
warm up for three hours.