DDR2(+LP) Compliance Testing Methods of Implementation
259
Data Timing Tests
16
tDS(base), Differential DQ and DM Input Setup Time - Test Method of Implementation
The purpose of this test is to verify that the time interval from the data or data mask (DQ/DM
rising/falling edge) setup time to the associated DQS crossing edge is within the conformance limits
as specified in the JEDEC specification.
Signals of Interest
Mode Supported: DDR2, LPDDR2
Signal cycle of interest: WRITE
Signal(s) of Interest:
• Data Signal (supported by Data Strobe Signal)
• Data Mask Signal
Optional signal(s):
• Chip Select Signal (this signal is used to separate DQ signals from different rank of memory)
Signals required to perform the test on the oscilloscope:
• Data Signal, DQ or Data Mask Signal, DM
• Data Strobe Signal, DQS (this must use a differential DQS connection)
• Chip Select Signal, CS (optional)
Test Definition Notes from the Specification
Table 172
Timing Parameters by Speed Grade (DDR2-400 and DDR2-533) & (DDR2-667 and DDR2-800)
Parameter
Symbol
DDR2-400
DDR2-533
Units
Specific Notes
Min
Max
Min
Max
DQ and DM input setup time (differential strobe)
tDS(base)
150
x
100
x
ps
6,7,8,20,28
Parameter
Symbol
DDR2-667
DDR2-800
Units
Specific Notes
Min
Max
Min
Max
DQ and DM input setup time
tDS(base)
100
x
50
x
ps
6,7,8,20,28,31
Table 173
Timing Parameters by Speed Grade (DDR2-1066)
Parameter
Symbol
DDR2-1066
Units
Specific Notes
Min
Max
DQ and DM input setup time
tDS(base)
0
x
ps
6,7,8,17,23,26
Table 174
Data Setup and Hold Base Values
Symbol
LPDDR2
Unit
Reference
1066
933
800
677
533
466
tDS(base)
-10
15
50
130
210
230
ps
V
IH/L(AC)
= V
REF(AC)
+/- 220mV
Summary of Contents for D9020DDRC
Page 1: ...Keysight D9020DDRC DDR2 LP Compliance Test Application Methods of Implementation ...
Page 10: ...10 DDR2 LP Compliance Testing Methods of Implementation ...
Page 46: ...2 Preparing to Take Measurements 30 DDR2 LP Compliance Testing Methods of Implementation ...
Page 70: ...3 Measurement Clock Tests 54 DDR2 LP Compliance Testing Methods of Implementation ...
Page 224: ...14 Clock Timing CT Tests 208 DDR2 LP Compliance Testing Methods of Implementation ...
Page 270: ...15 Data Strobe Timing DST Tests 254 DDR2 LP Compliance Testing Methods of Implementation ...