Commissioning
The inspections and tests to be performed on the electrical connections and
the correct functioning (in accordance with the locally applicable directives
and laws) may only be carried out by a qualified electrician.
The following work must be carried out before commissioning:
●
Remove all residual installation and connection materials from the con-
nection area.
●
Check all screw and clamp connections for tightness.
●
Check that all unused cable glands are properly sealed with blind plugs
or dummy screw fittings.
9.1
Perform safety checks
Before commissioning, check the effectiveness of the safety measure(s) of
the system according to the nationally applicable regulations.
Electrical systems or devices must be checked by the installer of the system
or device before commissioning. This also applies for the expansion or modi-
fication of existing systems or electrical devices. It is essential that all condi-
tions for the safety measures are observed.
For example, the following points are to be taken into account:
●
The checks (continuity of the connections of the protective conductor, in-
sulation resistance, RCD (FI) triggering current, triggering time, etc.) are
to be performed.
●
The measurement devices must comply with the national regulations!
●
The measurement results are to be documented. A test report is to be
created and saved before the check.