6.5
Installation
Hydraulic connection
Note the following points when connecting the hydraulic side:
Install and test safety components (expansion vessels, pressure relief valves and overflow valves).
Route condensation lines with a sufficient cross-section without bends and narrow sections with a gradient to the waste
water pipe on site.
Allow adequate space for the air flow (air inlet and outlet).
Pay attention to the following additional points with cooling mode:
Provide continuous vapour-tight insulation on all components that carry water (pipes, valves, connections) as far as the
unit.
Select appropriate pipe brackets (cooling clamps) for cooling mode.
Size the diameter of the condensation line appropriately.
Prevent any traps (if fitted) in the condensation line from drying out.