10. Number of height-adjustment feet and raised floor feet
Katherm HK
Trench length [mm]
Quantity of height-
adjustment feet
Quantity of raised floor
brackets
HK 320,
H 130 mm /
HK 290,
H 160 mm
2-pipe
/
4-pipe
915 /950*
2
2
1200
2
3
1700
2
4
2000
2
4
2500
2
5
3000
2
5
HK 360,
H 210 mm 2-pipe /
4-pipe
950
2
2
1200
2
3
1350
2
3
1850
2
4
2250
2
5
9.3.3 Condensation pump connection data
9.3.2 On-site condensation drainage with a condensation pump
The following drawing shows the on-site condensation connection of
the Katherm HK with condensation pump connected to a condensation
collecting pipe.
Max. delivery height
10 m
Max. pump volume
12 l/h
Supply voltage
230 V/50 Hz (separate mains supply
required)
Power consumption
16 W
Condensation pressure line
DN 6 mm (hose connection)
Signal contact for condensation overflow
Changeover contact, potential free;
Switching capacity 230 V/8 (5)A
* applies to Katherm HK 290
min 2% Gefälle
min 2% Gefälle
1
2
3
1
2
3
Kondensatanschluss Katherm HK - Sammelleitung
Kondensatsammelleitung
Achtung! Anschluss der Kondensatsammelleitung an das Schmutzwassernetz nach den
gültigen Normen und Regeln; Beachtung von notwendigen Entlüftungen,
Geruchsverschlüssen (Siphon), ect.
3
2
1
1
Katherm HK condensation connection – collecting pipe
2
Condensation collecting pipe
3
Important
: Connect the condensation collecting pipe to the waste water
network in accordance with all applicable technical standards and regulations;
note in particular any necessary vents, traps etc.
min. 2% gradient