Engineering of insulation
LFIS-B-1211
74
Installation
9. Engineering of insulation
9.1 Insulation of refrigerant pipe
9.1.1 Operational procedure of refrigerant pipe insulation
Cut the suitable pipe
→ insulation (except joint section) → flare the pipe → piping layout and connection→
vacuum drying
→ insulate the joint parts
9.1.2 Purpose of refrigerant pipe insulation
During operation, temperature of gas pipe and liquid pipe shall be over-heating or over-cooling
extremely. Therefore, it is necessary to carry out insulation; otherwise it shall debase the performance
of unit and burn compressor.
Gas pipe temperature is very low during cooling. If insulation is not enough, it shall form dew and cause
leakage.
Temperature of gas pipe is very high (generally 50-100
℃
) during heating. Insulation work must be
carried out to prevent hurt by carelessness touching.
9.1.3 Insulation material selection for refrigerant pipe
The burning performance should over 120
℃
According to the local law to choose insulation materials
The thickness of insulation layer shall be above 10mm.If in hot or wet environment place, the layer of
insulation should be thicker accordingly.
9.1.4 Installation highlights of insulation construction
Gas pipe and liquid pipe shall be insulated separately, if the gas pipe and liquid pipe were insulated
together; it will decrease the performance of air conditioner.
Liquid pipe
Insulation meterial
Gas pipe
The insulation material at the joint pipe shall be 5~10cm longer than the gap of the insulation material.
The insulation material at the joint pipe shall be inserted into the gap of the insulation material.
The insulation material at the joint pipe shall be banded to the gap pipe and liquid pipe tightly.
The linking part should be use glue to paste together
Be sure not bind the insulation material over-tight, it may extrude out the air in the material to cause bad
insulation and cause easy aging of the material.
9.2 Insulation of drainage pipe
9.2.1 Operational procedure of refrigerant pipe insulation
Select the suitable pipe
→ insulation (except joint section) → piping layout and connection→ drainage test→
insulate the joint parts
9.2.2 Purpose of drainage pipe insulation
The temperature of condensate drainage water is very low. If insulation is not enough, it shall form dew and
Summary of Contents for SUPER DC INVERTER SERIES
Page 1: ...Contents i New Energy Requirement SUPER DC INVERTER SERIES Service Manual 2012 LFIS B 1211 ...
Page 2: ...ii General Information ...
Page 4: ......
Page 17: ...LFIS B 1211 Service Space Indoor Units 13 3 Service Space 1000mm 1000mm 1000mm 1000m m ...
Page 23: ...LFIS B 1211 Field Wiring Indoor Units 19 9 Field Wiring ...
Page 36: ...Duct Type LFIS B 1211 32 Indoor Units 10 Field Wiring ...
Page 40: ...Duct Type LFIS B 1211 36 Indoor Units 3 Service Space ...
Page 44: ...Field Wiring LFIS B 1211 40 Part 3 9 Field Wiring ...
Page 50: ...Wiring Diagrams LFIS B 1211 46 Part 3 KOU 36HFN1 RRC4 ...
Page 100: ...Troubleshooting LFIS B 1211 96 Electrical Control System 2 4 2 3 Up down panel is not closed ...