Fig. 68 Fit the flexible pipe connection
1
Pipe
2
Seal holder
3
Gasket (seal ring)
4
Self-locking nut
5
Clamping screw
6
Self-locking nut
7
Pipe clamp halves
8
Sleeve
a
Pipe cut edge
b
Pipe sealing surface
d
Pipe diameter (outside)
s
Dimension of the flexible pipe joint under
tension.
Precondition The components to be connected must be flush-aligned.
The pipe must be deburred and the sealing face clean and undamaged. Point-shaped small con‐
cavities can be ignored, the axial direction must not exhibit any grooves.
1. Slide the seal holder
2
and gasket
3
over the pipe
1
.
2. Slide the pipe end
8
into the bush without pretension.
3. Ensure proper alignment of the pipe and push the sealing ring with sealing holder up to the
beveled edge of the sleeve.
4. Lay the pipe clamp halves
7
over the seal holder
2
and bush
8
and tighten the self-locking
nuts
4
until the dimension
s
is reached.
Pipe diameter: d [in]
Clamp diameter: s [in]
2.99
5.16
Tab. 77 Dimensions of the flexible pipe connection
5. Tighten up the clamping bolts
5
with the self-locking nuts
6
.
It must be just possible to manually move the screw connections.
10.6 Cleaning the cooler
The frequency of cleaning is mainly dependent on local operating conditions.
Severe clogging of the coolers causes overheating and machine damage.
Check coolers regularly for clogging.
Avoid creating dust eddies. Wear breathing protection if necessary.
Do not clean the coolers/radiators with a sharp instrument as they may be damaged.
A severely contaminated cooler/radiator should be cleaned by KAESER SERVICE.
10 Maintenance
10.6 Cleaning the cooler
No.: 9_9570 07 USE
Operator Manual Screw Compressor
M250 SIGMA CONTROL MOBIL
155