• AC power supply—Remove the power cord from the power supply faceplate by detaching the
power cord retainer and gently pulling out the plug end of the power cord connected to the
power supply faceplate.
• DC power supply—Loosen the thumbscrews securing the DC power connector on the power
source cables. Remove the power source cables from the power supply.
6. Remove any remaining cables and optics from the switch before removing it from the rack.
Removing a QFX10016 From a 4-Post Rack Using a Mechanical Lift
Before you remove the switch using a lift:
• Ensure that the rack is stable and secured to the building.
• Ensure there is enough space to place the removed switch in its new location and along the path to
the new location. See
QFX10000 Clearance Requirements for Airflow and Hardware Maintenance
.
• Review
"General Safety Guidelines and Warnings" on page 386
.
• Review the chassis lifting guidelines described in
QFX10002 Installation Safety Guidelines
.
• Ensure that the switch has been safely powered off.
CAUTION: When removing more than one switch chassis from a rack, remove the
switches in order from top to bottom.
Ensure that you have the following parts and tools available to remove the switch:
• A mechanical lift rated for 1000 lbs. (453.6 kg)
• A Phillips (+) screwdriver, number 2 or number 3, depending on the size of your rack-mounting
screws
Because of the switch's size and weight, we only recommend using a mechanical lift to install the
QFX10016.
To remove the switch using a mechanical lift (see
):
1. Use the appropriate Phillips (+) screwdriver to remove the 12 mounting screws that attach the
chassis front-mounting brackets to the rack.
2. Move the lift to the rack and position it so that its platform is centers about 0.5 in. (1.27 cm) below
the bottom of the switch chassis and as close to it as possible.
3. Carefully slide the switch from the adjustable mounting brackets attached to the rack onto the lift.
352
Summary of Contents for QFX10016
Page 1: ...QFX10016 Switch Hardware Guide Published 2022 09 09...
Page 10: ...Compliance Statements for Environmental Requirements 428 x...
Page 15: ...Figure 1 on page 5 shows a front and rear view of the QFX10016 4...
Page 16: ...Figure 1 QFX10016 Front and Rear 5...
Page 239: ...RELATED DOCUMENTATION QFX10008 Installation Overview QFX10002 System Overview 228...
Page 270: ...1 ESD point Figure 113 ESD Point on QFX10016 Chassis Rear 1 ESD point 259...
Page 287: ...Figure 130 Installing a JNP10K PWR AC2 in a QFX10016 276...
Page 322: ...Figure 159 Installing a JNP10K PWR DC2 in QFX10016 311...
Page 366: ...5 CHAPTER Troubleshooting Troubleshooting QFX10000 Modular Chassis 356...