The Scheduling feature offers different commands for Lighting Control
Groups than for other objects. The main difference is that alternate
weekly schedules and the one
-
time schedules are not available for
lighting control groups. Also, only four schedules per Lighting Control
object are allowed.
Scheduling a
Lighting Control
Group
1. Select a system, a lighting group, the SCHEDULE command,
NORMAL or HOLIDAY (these two options are mutually exclusive),
then ADD.
Adding a Schedule
2. Select a new schedule type:
Type 1--blinks at off time
Type 2--does not blink at off time
Type 3--overrides switch ON
Type 4--overrides switch OFF
3. Select the days of the week for the schedule to be in effect.
4. Enter the ON time.
5. Enter the OFF time.
After you press ENTER, the NT displays the new schedule for the group.
1. Select a system, a lighting group, the SCHEDULE option, then
NORMAL or HOLIDAY.
Modifying a
Schedule
2. Select a lighting schedule.
3. Select a new schedule type.
4. Select the days of the week for the schedule to be in effect.
5. Enter the ON time.
6. Enter the OFF time.
After you press ENTER, the NT displays the new schedule for the group.
50
Network Terminal User’s Manual