SECTION 3 - CHASSIS & TURNTABLE
3-46
– JLG Lift –
3120746
4. At the position indicated on Figure 3-36. try and
insert the 0.0015" feeler gauge between the bolt
head and hardened washer at the arrow indicated
position.
Wear Tolerance
1. From the underside of the machine, at rear center,
with the boom fully elevated and fully retracted, as
shown in (Figure 3-38., Swing Bearing Tolerance
Boom Placement) A, using a magnetic base dial
indicator, measure and record the distance between
the swing bearing and turntable. (Figure 3-37.,
Swing Bearing Tolerance Measuring Point)
2. At the same point, with the boom at horizontal and
fully extended, and the tower boom fully elevated as
shown in (Figure 3-38., Swing Bearing Tolerance
Boom Placement) B, using a magnetic base dial
indicator, measure and record the distance between
the swing bearing and turntable. (Figure 3-37.,
Swing Bearing Tolerance Measuring Point)
3. If a difference greater than 0.057 in. (1.40 mm) is
determined, the swing bearing should be replaced.
4. If a difference less than 0.057 in. (1.40 mm) is deter-
mined, and any of the following conditions exist, the
bearing should be removed, disassembled, and
inspected for the following:
a. Metal particles in the grease.
b. Increased drive power required.
c. Noise.
d. Rough rotation.
5. If bearing inspection shows no defects, reassemble
and return to service.
THE SWING BEARING IS ONE OF THE MOST CRITICAL POINTS
ON AN AERIAL LIFT. IT IS HERE THAT THE STRESSES OF LIFT-
ING ARE CONCENTRATED, AT THE CENTER OF ROTATION.
BECAUSE OF THIS, PROPER MAINTENANCE OF THE SWING
BEARING BOLTS IS A MUST FOR SAFE OPERATION.
Swing Bearing Replacement
1. Removal.
a. From Ground Control station, operate the boom
adequately to provide access to frame opening
or, if equipped, to rotary coupling.
NEVER WORK BENEATH THE BOOM WITHOUT FIRST ENGAGING
BOOM SAFETY PROP OR PROVIDING ADEQUATE OVERHEAD
SLING SUPPORT AND/OR BLOCKING.
b. Attach an adequate support sling to the boom
and draw all slack from sling. Prop or block the
boom if feasible.
c. From inside turntable, remove mounting hard-
ware which attach rotary coupling retaining yoke
brackets to turntable.
HYDRAULIC LINES AND PORTS SHOULD BE CAPPED IMMEDI-
ATELY AFTER DISCONNECTING LINES TO AVOID THE ENTRY OF
CONTAMINANTS INTO THE SYSTEM.
d. Tag and disconnect the hydraulic lines from the
fittings on the top of the rotary coupling. Use a
suitable container to retain any residual hydrau-
lic fluid. Immediately cap lines and ports.
.0015" Feeler Gauge
Figure 3-36. Swing Bearing Bolt Feeler Gauge Check
SWING
BEARING
FRAME REF.
TURNTABLE REF.
MEASURING
POINT
Figure 3-37. Swing Bearing Tolerance Measuring
Point
Summary of Contents for 601S
Page 1: ...Service and Maintenance Manual Model 601S P N 3120746 November 22 2016 ...
Page 2: ......
Page 4: ... JLG Lift THIS PAGE LEFT BLANK INTENTIONALLY ...
Page 16: ...x JLG Lift 3120746 TABLE OF CONTENTS Continued This page left blank intentionally ...
Page 26: ...SECTION 1 SPECIFICATIONS 1 10 JLG Lift 3120746 Figure 1 3 Torque Chart ...
Page 36: ...SECTION 2 GENERAL 2 10 JLG Lift 3120746 Figure 2 7 Connector Installation ...
Page 40: ...SECTION 2 GENERAL 2 14 JLG Lift 3120746 This page left blank intentionally ...
Page 49: ...SECTION 3 CHASSIS TURNTABLE 3120746 JLG Lift 3 9 Figure 3 1 Torque Hub Drive Fairfield ...
Page 51: ...SECTION 3 CHASSIS TURNTABLE 3120746 JLG Lift 3 11 Figure 3 2 Torque Hub Drive Auburn Gear ...
Page 53: ...SECTION 3 CHASSIS TURNTABLE 3120746 JLG Lift 3 13 Figure 3 3 Drive Brake Assembly Ausco ...
Page 91: ...SECTION 3 CHASSIS TURNTABLE 3120746 JLG Lift 3 51 Figure 3 40 Swing Brake Assembly Ausco ...
Page 99: ...SECTION 3 CHASSIS TURNTABLE 3120746 JLG Lift 3 59 ...
Page 119: ...SECTION 3 CHASSIS TURNTABLE 3120746 JLG Lift 3 79 Figure 3 46 EFI Component Location ...
Page 122: ...SECTION 3 CHASSIS TURNTABLE 3 82 JLG Lift 3120746 Figure 3 47 ECM EPM Identification ECM EPM ...
Page 128: ...SECTION 3 CHASSIS TURNTABLE 3 88 JLG Lift 3120746 This page left blank intentionally ...
Page 132: ...SECTION 4 BOOM PLATFORM 4 4 JLG Lift 3120746 Figure 4 5 Boom Assembly Cutaway Sheet 1 of 2 ...
Page 133: ...SECTION 4 BOOM PLATFORM 3120746 JLG Lift 4 5 Figure 4 6 Boom Assembly Cutaway Sheet 2 of 2 ...
Page 145: ...SECTION 4 BOOM PLATFORM 3120746 JLG Lift 4 17 Figure 4 22 Rotator Assembly Helac ...
Page 148: ...SECTION 4 BOOM PLATFORM 4 20 JLG Lift 3120746 This page left blank intentionally ...
Page 174: ...SECTION 5 HYDRAULICS 5 26 JLG Lift 3120746 This page left blank intentionally ...
Page 176: ...SECTION 6 JLG CONTROL SYSTEM ADE 6 2 JLG Lift 3120746 Figure 6 1 EPBCS Block Diagram ...
Page 238: ...SECTION 7 SCHEMATICS 7 16 JLG Lift 3120746 Figure 7 15 Hydraulic Schematic Sheet 1 of 4 ...
Page 240: ...SECTION 7 SCHEMATICS 7 18 JLG Lift 3120746 Figure 7 17 Hydraulic Schematic Sheet 3 of 4 ...
Page 242: ...SECTION 7 SCHEMATICS 7 20 JLG Lift 3120746 This page left blank intentionally ...
Page 243: ......