28
Service Manual
JL22
Installation method of brewer:
The two guide wheels at the bottom of the brewer should correspond to the two guide grooves on the brewer
drive. The two guide wheels of the brewer should be put into the guide grooves in the drive by holding the
brewer, and the brewer should be pushed backward, the clicking sound can be heard. Press the latch inward
with your finger to confirm whether the brewer latch is locked;
The brewer inlet pipe is inserted into the quick connector to the bottom; Click on the lower right
corner of the screen and click on [Settings] -> [Brewer] -> [Brewer Action Control ]-> [init]; When the
brewer completes the action, abnormal standby will appear in the middle of the screen.
10.8
Maintenance Guidelines
10.8.1
Empty boiler
Pull out the water tray, turn on the drain switch, install the water tray, enter the password into the
background, disconnect the water source connected to the machine or unplug the pump power plug,
click the lower right corner [cleaning], click [empty boiler]. After waiting for five minutes, close the
door and unplug the machine.