5
Installation
5.8
Power
cabling of the lithium-ion batteries
INTILION scalebloc 0.5C
59
5.8
Power cabling of the lithium-ion batteries
DANGER
Risk to life
Working on live equipment when wiring up the lithium-ion batteries involves
fatal risks e.g. due to arcs or electric shocks.
•
Installation by qualified specialists is prohibited without valid WLE
certification in accordance with DGUV Rule 103-011/3.2.4 and
VDE 0105-100 Section 6.3.2
•
For safety reasons (among others), installation is prohibited
without valid training by INTILION GmbH.
•
Wear arc-proof work clothing, 1000V protective gloves, safety
boots and a safety helmet with visor to protect against arcs. The
visor must be kept closed at all times when carrying out
subsequent work.
•
Use only insulated tools.
•
Place at least one 1.5 m x 1.5 m rubber mat in front of the battery
storage system.
The enclosed wiring diagram shows the wiring of the lithium-ion batteries and the
battery management system (BMS). The pre-assembled cable package A is
required for the wiring work. The cable package A contains all of the cables
(power cable and ventilator/communication cable) that are required in order to
connect the lithium-ion batteries to the battery management system.
Summary of Contents for scalebloc 0.5C
Page 33: ...2 Safety 2 10 Obligations of the system manager INTILION scalebloc 0 5C 31 ...
Page 34: ......
Page 46: ...4 Transport and storage 3 3 Technical specifications 44 INTILION GmbH ...
Page 77: ...5 Installation 5 12 Establishing the mains connection INTILION scalebloc 0 5C 75 ...
Page 78: ......
Page 98: ...6 Commissioning 6 8 Contacting the Hoppecke Service team 96 INTILION GmbH ...
Page 100: ......
Page 102: ...8 Fault 100 INTILION GmbH ...