Installation Steps
Step 1:
Unpack the Industrial Fast Ethernet Switch.
Step 2:
Check the DIN-Rail is screwed on the Industrial Fast
Ethernet Switch. (Please refer to DIN-Rail Mounting section for
DIN-Rail installation. If you want to wall mount the Industrial
Fast Ethernet Switch, then please refer to Wall Mount Plate
Mounting section for wall mount plate installation.
Step 3:
To hang the Industrial Fast Ethernet Switch on the
DIN-Rail track or wall, please refer to the Mounting Installation
section.
Step 4:
Power on the Industrial Fast Ethernet Switch. (Please
refer to the Wiring the Power Inputs section for power input)
The power LED on the Industrial Fast Ethernet Switch will
illuminate. Please refer to the LED Indicators section for
meaning of LED lights.
Step 5:
Prepare the twisted-pair, straight through Category 5
cable for Ethernet connection.
Step 6:
Insert one side of Category 5 cables into the Industrial
Fast Ethernet Switch Ethernet port (RJ-45 port) and the other
side to the network devices Ethernet port (RJ-45 port), ex:
Switch, PC or Server. The UTP port (RJ-45) LED on the
Industrial Fast Ethernet Switch will illuminate when the cable is
connected with the network device. Please refer to the LED
Indicators section for LED light meaning.
Step 7:
Insert fiber cable from the MC250-4T series to the
fiber network. The TX and RX or the SFP modules for MC250-
4T/2S, must be paired at both ends. The optical port LED on
the Industrial Fast Ethernet Switch will illuminate when the
cable is connected to the network device. Please refer to the
LED Indicators section for the LED descriptions.
Step 8:
When all connections are set and the LEDs are
illuminated without any issues the installation is completed.