Platform Installations and Upgrades
Intel
®
Carrier Grade Server TIGI2U User Guide
35
Removing and Installing the Chassis Cover
Removing the Chassis Cover
The Intel
®
Carrier Grade Server TIGI2U must be operated with the top cover in place to
ensure proper cooling. You will need to remove the top cover to add or replace
components inside of the platform. Before removing the top cover, power down the server
system and unplug all peripheral devices and the AC power cable or disconnect the DC
mains. None of the components inside the platform are hot-swappable.
To mitigate damage to equipment from static electricity discharge an antistatic wriststrap
connected to earth ground must be worn be service personnel.
NOTE
A nonskid surface or a stop behind the platform may be needed to
prevent the platform from sliding on your work surface.
1. Observe the safety and ESD precautions at the beginning of this section.
2. Turn off all peripheral devices connected to the server. Turn off the server.
3. Disconnect the AC power cord or disconnect the DC mains.
4. While holding the blue button at the top of the chassis in (see letter “A”), slide the top
cover back until it stops (see letter “B”).
5. Lift the cover straight up to remove it from the platform.
Figure 10. Removing the Chassis Cover
Summary of Contents for TIGI2U - Carrier Grade Server