Warnings!

15kg

30kg

50kg

For devices ≥ 15kg, it requires at least 2 people. 

For devices ≥ 30kg, it requires at least 3 people. 

For devices ≥ 50kg, it requires at least 4 people.

Watch out for the scratches that may be caused by the cabinet, 
chassis or rails.
Be aware of electric shock when installing the servers into the 
cabinet in use.

Rack-Mounted Server

Installation Guide

V1.0

DO NOT block the vents on the server during installation, especially the vents on the 

front and rear of the server.

Remove the protective film from the chassis before installing servers into the rack.

For proper ventilation, leave a minimum space of 15cm between two servers.

For easy access of the front and rear ports and cabling, leave a minimum space of

70mm between the front side of the server and the inner side of the cabinet’s front
door, and 150mm between the rear side of the server and the inner side of the
cabinet’s rear door.

Always keep the air baffles in place to ensure proper air flow and avoid air 

turbulence in the server room.

Installation must comply with local and regional electrical regulations. To reduce the 

risk of personal injury, fire, or damage to the server, DO NOT overload the AC supply
that provides power to the rack.

Servers can only be deployed in dedicated cabinets with ventilation holes or

specialized cooling cabinets to avoid server failure from overheating as they are high
power appliances.

In case of multiple-server deployment, always load from bottom to top and place the 

heavier server on the lower bay.

DO NOT install devices beyond the cabinet’s load-bearing capacity, power supply 

capacity and heat dissipation capacity.

Please keep this document for future reference.