BOILER START
-
UP
(
IGNITION
)
.
To commission the boiler (the operations listed below must only be
performed by qualified personnel and in the presence of staff only):
- check that the internal system is properly sealed according to
the specifications set forth by regulations in force;
- ensure that the type of gas used corresponds to the boiler settings
(the type of gas appears on the display on first electrical power supply,
or by checking the relative parameter “G”);
- check that there is no air in the gas pipe;
- check connection to a 230V-50Hz power mains, correct L-N polarity
and the earthing connection;
- check that the intake/exhaust terminals are not obstructed and
that they are installed properly;
- check that the drain trap is full and that it prevents any passage
of
fl
ue gas into the room;
- check that there are no external factors that may cause the formation
of fuel pockets;
- perform the
fl
ue test and, if needed, set the correct value of the
parameter “F0” (Par. 3.14);
- activate the quick calibration function (Par. 3.13);
- switch the boiler on and ensure correct ignition;
- make sure that the gas
fl
ow rate and relevant pressure values
comply with those given in the manual (Par. 4.1);
- ensure that the safety device intervenes in the event of gas supply
failure and check the relative intervention time;
- check the intervention of the main switch located upstream from
the boiler and in the boiler.
Th
e system must not be started up if even only one of the checks
should be negative.