Recommendations for terminal implementation
Every installation is unique. Sometimes the issues are well defined and can be handled
in a standard fashion; sometimes the issues are very specific and may not be
immediately recognizable.
IDEMIA recommends following these steps for a successful installation:
Plan the installation - Choose the type of hardware required, decide if a network is
required, and decide on the location and number of required terminals.
Unpack all items - Unpack all items and check against the packing list.
Install network hardware components - Install the cabling and components
needed to run the system.
Install software - Install the software needed to set up the terminals.
Pre-configure device - Connect the terminals to the Ethernet, supply power to the
terminals, and pre-configure the terminals.
Mount devices - Mount the terminals in their final locations
Power distribution and device hook up - Connect the terminals wiring via the back
panel.
Power-up procedure - Check the power connections, and then start the system
safely.