Installation & Maintenance 

Principle 

The NET-BOX device is designed to be fitted near a guarded access point where a mix of safe and standard 
IO control functions are required. The NET-BOX is fitted with an (optional) E-Stop and can monitor external 
dual channel safety devices that are equipped with either voltage-free contacts (NET-BOX provides test 
pulses) or OSSD outputs. A single dual channel output is also provided for safe control of an actuator. 

 

WARNING 

DO NOT DEFEAT, TAMPER, OR BYPASS THE SAFETY FUNCTION.  
FAILURE TO DO SO CAN RESULT IN DEATH OR SERIOUS INJURY. 
 
NE PAS DESACTIVER, MODIFIER, RETIRER, OU CONTOURNER CETI, INTERVERROUILLAGE 
IL PEUT EN RESULTER DES BLESSURES GRAVES DU PERSONNEL UTILISATEUR. 
 

 

Observe the county-specific regulations when installing the device. 

 

Repair or modification of the NET-BOX is not allowed unless authorised by IDEM and 
carried out according to operating guidelines. 

 

Safety critical failures which do not lead to the safe state shall be reported to IDEM 
immediately. 

 

Replace a malfunctioning NET-BOX immediately. 

 

NOTES REGARDING  

  : 

 

Maximum Temperature 40°C 

Fastening 

 

IMPORTANT 

 

The tightening torque to ensure reliable fixing is 4.0Nm. 

Maintenance Activities 

 

IMPORTANT 

 

To achieve the target safety level, it is required to routinely check the safety 
functions are operating correctly. For applications targeting PLe a check should take 
place once per month, for PLd applications a check should take place once per year. 

 

If any part of the NET-BOX displays mechanical damage then remove and replace. 

 

IDEM will not accept responsibility for failure of the device functions if the 
installation and maintenance requirements shown in this document are not correctly 
implemented.  

 

Summary of Contents for NET-BOX-CS

Page 1: ...nstructions To request this document in other languages please contact info idemsafety com IDEM Safety Switches NET BOX CS Safety IO Standard IO and Integrated EtherNet IP with CIP Safety Operating In...

Page 2: ...col Setup 4 Network Address Setup Initial Setting 5 Setting via DIP Switch 5 Setting via DHCP 6 Studio 5000 Ethernet IP Configuration 7 Factory reset 9 Functional Tests 9 6 Data Map 9 7 Diagnostic Ind...

Page 3: ...idiaries and affiliates are not in a position to guarantee all of the characteristics of a given system or product not design by IDEM All relevant safety regulations and standards are to be observed T...

Page 4: ...ISATEUR Observe the county specific regulations when installing the device Repair or modification of the NET BOX is not allowed unless authorised by IDEM and carried out according to operating guideli...

Page 5: ...irements for UL a class 2 power supply must be used INFORMATION When multiple devices are used in a daisy chain arrangement the power bus may be forwarded via the NET BOX device See technical specific...

Page 6: ...ASYNC parameter value of 1 Configuring an originator with connection data and or target configuration data must be downloaded to the target so it can be tested and verified Only then can SCIDs from t...

Page 7: ...the final step if the device is powered Remove the lid screws and turn over the NET BOX Lid to locate the DIP switches see below Using a small tool push the required switches to the ON position to set...

Page 8: ...entify the NET BOX select the NET BOX in the Discovery History window and click Add Relation 4 Configure the required IP address setting in the pop up window and click OK 5 Open an internet browser an...

Page 9: ...Configuration 1 Download the EDS file for the NET BOX and import to application control software 2 Open or create a project with the PLC CPU Partner and Ethernet IP modules added 3 Right click the Et...

Page 10: ...customisable NET BOX CS used as example only and set the previously configured IP address 6 Change the Safety Network Number SNN to match that of the controller PLC 7 On the Safety tab uncheck the Con...

Page 11: ...ce has been installed and setup within the EtherNet IP CIP Safety application control software the following checks are necessary to ensure correct operation of the system Secure mounting of NET BOX w...

Page 12: ...on to PLC Idle state Red Major Fault Red Flashing Recoverable fault check PLC NET BOX configuration NS Off No IP address set Green Online connection s established Green flash 1Hz Online no connections...

Page 13: ...ge 24V DC Input Rated Current 2 mA Standard Outputs Output Rated Voltage 24V DC sourced from power connectors Output Maximum Current 500 mA single 1 5 A group OUT1 4 OUT5 8 Test Outputs Parameter Unit...

Page 14: ...altitude 2000 m Shock and Vibration Tested in accordance with IEC 60068 2 6 and IEC 60068 2 27 Pollution Degree Degree 2 EN 60664 Storage and Operation Reliability Safety Data EN ISO 13849 1 Category...

Page 15: ...Operating Instructions IDEM Safety Switches NET BOX CS 102638 2305 NET BOX CS Operating Instructions 13 NOTES...

Page 16: ...BOX THE LISTED DEVICES CONFORM TO THE ESSENTIAL HEALTH AND SAFETY REQUIREMENTS OF THE FOLLOWING EUROPEAN DIRECTIVES AND STANDARDS DIRECTIVES Machinery Directive 2006 42 EC EMC Directive 2014 30 EU ST...

Reviews: