Installation
19
BURNER ASSEMBLY
For the activities listed below, concerning the burner:
–
installation and fastening to the Boiler
–
the connection to the fuel supply
–
the electrical connections
–
the adjustments to be made
–
maintenance
–
the necessary checks.
refer to the Manual supplied with the appliance.
m
IMPORTANT
Insert the thermoceramic material strip, supplied with the insulating casing, into the gap between the burner
combustion head and the door. The strip must be wrapped around the combustion head for at least one entire
circumference, without having to fill the whole thickness of the gap.
1
4
5
3
2
6
1
Burner
2
Flange
3
Gasket
4
Door
5
Thermoceramic material
6
Combustion head
ELECTRICAL CONNECTIONS
The electrical system of
CODEX GT
Boilers must be built by an Authorised Company that must refer to the wiring diagrams
supplied with the Boiler, with the control panel and with the burner. Moreover, it must operate in compliance with the Technical
Standards and the national and local Laws in force.
Once the work is complete, the Authorised Company must issue the
Declaration of Conformity
of the system built.
m
IMPORTANT
It is mandatory to:
–
use an omnipolar thermal-magnetic line circuit breaker complying with the Standards CEI-EN (contact opening of at
least 3 mm)
–
observe the connection L (Phase) - N (Neutral). Keep the earth conductor longer than the power supply conductors by
approximately 2 cm
–
connect the earth cable to an effective earthing system.
ICI Caldaie S.p.A.
is not liable for any damage caused by the
lack of the earthing system and the failure to comply with the instructions of the wiring diagrams.
d
PROHIBITION
Do not use the water and heating system pipes for the
earthing connections
.
Cooke Industries - Phone: +64 9 579 2185 Email: [email protected] Web: www.cookeindustries.co.nz