Note:
Your order information is included with your product. You can also obtain order
information from your marketing representative or the IBM Business Partner.
If you have incorrect, missing, or damaged parts, consult any of the following resources:
v
Your IBM reseller.
v
IBM Rochester manufacturing automated information line at 1-800-300-8751 (United States only).
v
The Directory of worldwide contacts website http://www.ibm.com/planetwide. Select your
location to view the service and support contact information.
Determining and marking the location in the rack
Water-cooled systems have unique rack location requirements. Where you mount the system is dependent
on whether your water hoses are routed toward the top or the bottom of the rack.
A rack-mounting template is not included with this system. These systems are 2 Electronic Industries
Alliance (EIA) units high.
To determine the mounting location, complete the following steps:
1.
Read the Rack safety notices (http://www.ibm.com/support/knowledgecenter/POWER8/p8hbf/
racksafety.htm).
2.
Determine where to place the system unit in the rack. As you plan for installing the system unit in a
rack, consider the following information:
v
Organize larger and heavier units into the lower part of the rack.
v
Plan to install units into the lower part of the rack first.
v
Record the Electronic Industries Alliance (EIA) locations in your plan.
Note:
The server is two EIA units high. An EIA unit is 44.55 mm (1.75 in.) in height. The rack
contains three mounting holes for each EIA unit of height. This system unit, therefore, is 89 mm (3.5
in.) high and covers six mounting holes in the rack.
3.
If the hoses on the rack are routed so that they go down the rack toward the floor, you choose one
of the following options:
v
Ensure that the bottom EIA unit is left open. If you choose this option, the bottom of the system
chassis should align with an even EIA unit number on the rack flange.
v
Ensure that the bottom two EIA units are left open. If you choose this option, the bottom of the
system chassis should align with an odd EIA unit number on the rack flange.
4.
If the hoses on your rack are routed so that they go up through the top of the rack, ensure that the
top two EIA units are left open. The bottom of the system chassis that you are installing should align
with an odd EIA unit number on the rack flange.
5.
If necessary, remove the filler panels to allow access to the inside of the rack enclosure where you
plan to place the unit, as shown in Figure 18 on page 20
Installing the IBM Power System S822L (8247-22L)
19
Summary of Contents for Power System 8247-22L
Page 1: ...Power Systems Installing the IBM Power System S822L 8247 22L GI11 9908 06 IBM ...
Page 2: ......
Page 3: ...Power Systems Installing the IBM Power System S822L 8247 22L GI11 9908 06 IBM ...
Page 16: ...xiv Power Systems Installing the IBM Power System S822L 8247 22L ...
Page 62: ...46 Power Systems Installing the IBM Power System S822L 8247 22L ...
Page 74: ...58 Power Systems Installing the IBM Power System S822L 8247 22L ...
Page 75: ......
Page 76: ...IBM Part Number 01LK526 Printed in USA GI11 9908 06 1P P N 01LK526 ...