Planning activities
You can use this information to help you plan the physical installation for your server.
Proper planning for your system will facilitate a smooth installation and fast system start-up. Sales and
installation planning representatives are also available to help you with installation planning.
As part of your planning activity, you will make decisions about where to locate your server and who
will operate the system
Planning task checklist
Use this checklist to document your planning progress.
Working with your sales representative, establish completion dates for each of the tasks. You might want
to review your planning schedule periodically with your sales representative.
Table 1. Planning task checklist
Planning step
Person responsible
Target date
Completion date
Plan your office or computer
room layout (physical planning)
Prepare for power cords and
electrical needs
Prepare for cables and cabling
Create or modify communications
networks
Perform building alterations, as
needed
Prepare maintenance, recovery,
and security plans
Develop an education plan
Order supplies
Prepare for system delivery
General considerations
Planning your system requires attention to the numerous details.
When determining the placement of your system, consider the following:
v
Adequate space for the devices.
v
Working environment of personnel who will be using the devices (their comfort, ability to access the
devices, supplies, and reference materials).
v
Adequate space for maintaining and servicing the devices.
v
Physical security requirements necessary for the devices.
v
Weight of the devices.
v
Heat output of the devices.
v
Operating temperature requirements of the devices.
© Copyright IBM Corp. 2015, 2016
3
Summary of Contents for 8408-44E
Page 1: ...Power Systems Site and hardware planning IBM...
Page 2: ......
Page 3: ...Power Systems Site and hardware planning IBM...
Page 16: ...xiv Site and hardware planning...
Page 18: ...2 Site and hardware planning...
Page 22: ...6 Site and hardware planning...
Page 51: ...Figure 19 Model 0555 and 7014 S25 plan view Site and hardware planning 35...
Page 192: ...176 Site and hardware planning...
Page 204: ...188 Site and hardware planning...
Page 205: ......
Page 206: ...IBM Printed in USA...