Manual ibaBM-SLM
10
Initial operation
10.1
Basic Steps
For initial operation proceed as follows:
1.
Mount the ibaBM-SLM device
2.
Prepare the ibaPDA computer (insert the ibaFOB card, install ibaPDA-V6 software)
3.
Integrate ibaBM-SLM into the SIMOLINK bus (establish the connections)
4.
Connect the device to the ibaPDA computer via the serial interface with a V.24 inter-
face cable.
5.
Establish the FO connection to the ibaPDA computer.
6.
Connect the 24V power supply, and if required, connect also the SIMOLINK module
to a 24V power supply.
7.
Switch on the power supply.
8.
Start ibaPDA.
9.
Configure all required settings in ibaPDA.
10.
If you want to test whether the device is sending data to the ibaPDA computer, you
can use the simulation function of the device.
11.
Remove all serial connections when signal recording is active.
The following chapters describe the basic steps and the required settings for con-
figuration in ibaPDA and ibaAnalyzer in a more detailed way.
For further information please refer to the further manuals.
10.2
Configuration in ibaPDA
10.2.1
Hardware Configuration
10.2.1.1 Interfaces and input signals
The I/O Manager is the central dialog for the connection of the device to the ibaPDA
computer (ibaFOB-D card) and all settings of the input signals and the interfaces.
For further information refer to ibaPDA manual.
Proceeding
1.
Open the I/O Manager
2.
Select the “Hardware” menu.
3.
In the left module tree mark the ibaFOB-D card, the device is connected to.
18
Issue 2.0