6 Putting the FCU into operation
Before operation, the FCU must first be hydraulically and elec-
trically connected, as described below.
6.1 Connecting / disconnecting the power supply
The FCU has a 3-pole socket for connection with a 24 V DC
power supply.
Fig. 15:
Connecting the
power supply
1.
Insert the 3-pole socket plug, e.g. of the power pack,
into the socket until the ratchet can be heard to click in
(
). Connect the other end with the voltage
source.
2.
Once the FCU is supplied with voltage, the display will
show "HYDAC FCU 1210" in ticker format, after which
the Firmware version will be displayed for 2 seconds.
The internal sensors are subsequently checked.
The self-test is followed in the display by a countdown
.
3.
The FCU is now ready for the measurement.
As long as the pump is not running and no fluid
is being pumped, the status LED will flash red,
and the display will show
. This
means that there is no oil flow present.
6.1.1 Disconnecting the power supply
To remove the power supply, press the catch (1) on the con-