5.1 | PRE-START INSPECTION
Before use each day or at the beginning of each shift, the machine shall be given a visual inspection and functional
test. Repairs (if any) must be made prior to operating the machine, as it is critical to ensure safe operation of the
machine. A checklist for pre-start inspection can be found in the back of this manual.
5.2 | CONTROLS
SECTION 5 | OPERATION
Item # Control/Indicator
1
Master Power Switch/Emergency Stop
FIGURE 9: Base Controls
Item # Control/Indicator
1
Up/Down Rotary Switch
Operation described as follows
2
Emergency Stop
Operation described in Section 2.4
3
Overload Indicator Light
4
Battery Voltage Meter
5
Lift Enable Button
Operation described as follows
6
Alarm Sounds for descent, overload
FIGURE 10: Platform Controls
1
2
3
4
5
6
OPERATIONS & SAFETY
HB-P527
SUPO-723
REV C
BY CUSTOM EQUIPMENT LLC
16