Figure 3-72 Equipment layout in the end IT cabinet
Procedure
Step 1 Determine the mounting holes for the ECC800-Pro on the end IT cabinet, adjust
the guide rails, and install floating nuts.
Figure 3-73 Installing a floating nut
Step 2 Place the ECC800-Pro in the IT cabinet with caution.
Step 3 Secure the ECC800-Pro in the IT cabinet by tightening the M6 screws on the
mounting ears.