Step 3
Remove the left and right side panels from the input and output unit.
Step 4
Combine the power units, bypass unit and input/output units, and install the connecting plates
in the following sequence: bottom, top, and middle.
Figure 3-10
Installing connecting plates
Step 5
Install the side panels removed from the input and output unit to power unit 1 and power unit
3.
Step 6
Use M12x60 expansion bolts to secure the power units, bypass unit, and input/output units to
the expansion bolt mounting holes on the floor in sequence.
Step 7
Install anchor baffle plates.