3 Installation
Issue 04 (2020-03-03)
Copyright © Huawei Technologies Co., Ltd.
53
Tools and Meters
Phillips screwdriver
(M3/M4/M5/M6/M
8)
Insulated torque
wrench
(M6/M8/M12/M16)
Heat shrink tubing
Insulated adjustable
wrench
Table 3-1 lists only the common tools for installation and cable connection. For more dedicated tools
required, see the corresponding component manuals. Prepare tools based on site requirements.
3.1.3 Preparing Power Cables and Copper Bars
The UPS can generate large leakage currents. A circuit breaker that provides leakage current
protection is not recommended.