UPS5000-E-(25 kVA-75 kVA)-BF
User Manual
3 Installation
Issue 07 (2019-12-13)
Copyright © Huawei Technologies Co., Ltd.
93
Step 7
Push the upper cover forwards as shown in the following figure to reinstall it, and screw it.
Figure 3-66
Reinstalling the upper cover
----End
3.5 Installation Verification
If the check results of listed items 8 and 9 in
do not meet the acceptance criteria,
the UPS may be damaged.
Table 3-10
Installation checklist
No.
Item
Acceptance Criteria
01
UPS installation
The UPS is securely installed and does not tilt
due to vibration.
02
Neat arrangement
The UPS and its adjacent cabinets are neatly
arranged and secured with connecting plates.
03
Cable layout
Cables are routed properly and cable routing
meets customer requirements.
04
Cable labels
Both ends of a cable are labeled. Labels are