UPS5000-E-(25 kVA-75 kVA)-SM
User Manual (Half Height)
3 Installation
Issue 03 (2019-12-13)
Copyright © Huawei Technologies Co., Ltd.
48
Figure 3-6
Lowering the leveling feet
Step 2
Check the cabinet levelness using a level. If the cabinet is not leveled, adjust the leveling feet.
Step 3
To prevent misoperations, you are advised to configure locks (with the diameter of the valid
lock cylinder being 5–10 mm) for the maintenance bypass switch.
----End
Securing the UPS Using L-shaped Brackets
L-shaped brackets and antiseismic kits cannot coexist. If the antiseismic kit is configured, the
installation scenario cannot be secured using L-shaped brackets.
Step 1
Determine the position for installing the UPS. Mark mounting holes and their dimensions
based on the marking-off template.