3.5.4 End-to-End Configuration Process
This topic describes how to configure 1:1 linear MSP services in an end-to-end manner.
Prerequisite
l
The physical network topology must be set up.
l
NEs, boards, and fibers must be successfully created on the U2000.
l
A linear MSP subnet must be created and must be the same as the actual topology. For
details about how to create a protection subnet, see
2.6.4 Creating a Linear MS Protection
l
The operator must understand the information provided in
3.5.2 Signal Flow and Timeslot
Procedure
Step 1
Choose
Service
>
SDH Trail
>
Create SDH Trail
from the Main Menu.
Step 2
Create the VC-4 service-layer trail.
1.
Configure the parameters as follows. Set
Level
to
VC4 Server Trail
. The other parameters
take default values.
2.
Double-click the source NE (NE1) and sink NE (NE2) on the right of the main topology
and click
Apply
. In the
Operation Result
dialog box indicating that the operation
succeeded, click
Close
.
3.
Optional:
In the
Operation Result
dialog box indicating that the operation succeeded,
click
Browse Trail
to query the created VC4 service-layer trail.
Step 3
Create VC12 services.
1.
In
Create SDH Trail
, configure the parameters as follows. Set
Level
to
VC12
. The other
parameters take default values.
2.
Double-click the source NE (NE1) on the right of the main topology. The
Select Board
Port-Source
dialog box is displayed. Select the required SP3D board and
Tributary
Port
. Click
OK
.
3.
Double-click the sink NE (NE2) on the right of the main topology. Configure NE2 in the
same manner.
OptiX OSN 550 Multi-Service CPE Optical Transmission
System
Configuration Guide
3 Configuring SDH Services
Issue 02 (2011-06-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3-25