3 Installation
Issue 07 (2020-03-16)
Copyright © Huawei Technologies Co., Ltd.
40
Figure 3-16
Removing the connecting kit that secures the cabinet to the pallet
1.
Use a 10# socket wrench to remove eight M6x16 bolts that secure the connecting kit to
the cabinet.
2.
Use an 18# socket wrench to remove four M12x35 bolts that secure the connecting kit to
the pallet.
3.
Remove the connecting kit.
Save the removed bolts for future use.
Step 2
Transport the cabinet to the specified position. You are advised to use a pallet truck to
transport devices.
Exercise caution when moving the cabinet to prevent falling down.
----End
3.6 Leveling and Combining Cabinets
Procedure
Step 1
Level the cabinet. Use a socket wrench to adjust the leveling feet at the bottom of the smart
cooling product, and use a measuring tape and a level to adjust the horizontal and vertical
distances of the smart cooling product. Ensure that the leveling feet touch the floor after
adjustment, as shown in