Figure 4-2 Floor-mounted installation dimensions
Procedure
Step 1 Align the floor support with the wall surface and keep the support 10 mm to 15
mm away from the wall surface. Level the hole positions using a level, and mark
the hole positions for installing the floor support using a marker. Align the
marking-off template with the surface of the floor mounting kit, determine the
drilling hole positions on the wall for securing the power control module, and
mark the positions using a marker.
Step 2 Install the floor support.
D ANGER
When drilling holes, avoid the water pipes and power cables buried in the wall.
NO TE
M6x60 expansion bolts delivered with the battery are used to install the floor support and
power control module. If the length and quantity of the bolts do not meet installation
requirements, prepare M6 stainless steel expansion bolts by yourself.
LUNA2000-(5-30)-S0
User Manual
4 System Installation
Issue 01 (2020-10-20)
Copyright © Huawei Technologies Co., Ltd.
40