FusionModule800 Smart Small Data Center
Installation Guide (Six Fans)
6 Power-On Commissioning
Issue 10 (2019-12-20)
Copyright © Huawei Technologies Co., Ltd.
241
Path
Parameter
Name
Setting
port connected to the independent deployment AI_DI unit.
Device
address
In this example,
Device address
is set to
1
. During
actual configuration, set the device address for the
independent deployment AI_DI unit based on the
actual situation.
Step 3
Click
Test Connect
to check whether the standalone AI/DI module connects to the ECC800
properly.
If the independent deployment AI_DI unit connects to the ECC800 properly, click
Confirm
.
If the independent deployment AI_DI unit is not properly connected to the ECC800,
check whether the cable between the standalone AI/DI module and the ECC800 is
connected properly, whether the standalone AI/DI module and ECC800 are running
properly, and whether the input parameters are the consistent with the external AI/DI
module parameters.
----End
6.3.6 Commissioning the Sensor
6.3.6.1 Commissioning the Smoke Detector
Procedure
Step 1
Set smoke sensor parameters.
The parameter has been preset before delivery.
In this example, the smoke detector is connected to the AI/DI_1 port on the skylight actuator.
1.
Log in to the ECC800 WebUI as an administrator.
2.
Choose
System Settings
>
Signal Name Modify
. The
Batch Signal Configuration
page is displayed.
3.
Set
Device type
to
ECC800
, set
Device name
to
ECC800
, and click
OK
.
4.
On the query result tab page, set the new signal name of
AI/DI_3
to
Smoke
and click
Submit
.
5.
Choose
Monitoring
>
System
>
ECC800
>
Running Parameters
>
AI/DI_3 Port
Settings
.
6.
Set
Smoke sensor
to
Enable
and click
Submit
.
7.
Confirm that
Smoke sensor type
is automatically identified as
Smoke Sensor
or
Smoke
sensor(NC)
. Ensure that
Smoke power supply
is
Yes
.
Step 2
Check the monitoring functions of smoke sensor.