FusionModule800 Smart Small Data Center
Installation Guide (Six Fans)
6 Power-On Commissioning
Issue 10 (2019-12-20)
Copyright © Huawei Technologies Co., Ltd.
235
Table 6-3
Set UPS parameters
Parameter
Default Value Setting Value
Batteries (10 kVA
UPS)
Positive
batteries/Negative
batteries (20 kVA
UPS)
20
Set as required.
Battery capacity
65 Ah
Battery capacity = Capacity of a single battery
string x Number of parallel battery
strings/Number of parallel UPSs sharing a battery
string.
Note: use two UPSs sharing a 65 Ah battery string as an example: if the calculated battery
capacity is (65 x 1)/2 = 32.5, set it to 32 Ah.
For details about how to operate the UPS, see the manual delivered with the UPS.
Step 6
Turn on the UPS output switch after the UPS starts.
Step 7
Switch on the PDU2000 circuit breakers one by one on the PDU and switch on the PDU2000
circuit breaker in the rear of the cabinet to power on corresponding devices.
When switching on the circuit breakers, observe whether there is any abnormal phenomenon,
such as sparks.
Step 8
Switch on the ECC circuit breaker on the PDU to power on the ECC.
Step 9
Switch on the smart cooling product circuit breaker on the PDU to power on the smart cooling
product.
----End
6.3 Management System Power-On Commissioning
6.3.1 Preparations and WebUI Login
Prerequisites
User rights:
The default user with administrator rights is admin. The preset password is Changeme.
The admin user has all WebUI operation rights.