FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
5 Installing the Cabinet
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
68
Figure 5-6
Leveling a cabinet
(1) Level
Step 3
Interconnect adjacent cabinets, as shown in
1.
Remove the M5x10 tapping screws that secure the connecting kits and then remove the
connecting kits.
2.
Remove M4x10 screw assemblies from the position for combining cabinets.
3.
Secure the connecting kit using the M4x10 screw assemblies.