FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
9 Installing Monitoring Devices
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
120
Figure 9-14
Connecting an antenna cable
Figure 9-15
Antenna route inside a cabinet
Step 6
Connect the ECC800 power cable to the PDU2000.
----End
9.6 (Optional) Installing a Rack Environment Unit
Context
Install a rack environment unit on the rack rail of the cabinet rear door.