(Optional) Installing Bases
4.1 Precautions for Installing Bases
To ensure that bases fit cabinet connecting structures, configure bases with different
specifications for different cabinets. For the detailed dimensions of bases, see the installation
diagrams and parameter manual.
Choose either bases with adjustable dimensions or bases with fixed dimensions.
If there are bases, install air conditioners first.
If there are no bases, install cabinets from the end cabinet in sequence.
If you do not use the bases provided by Huawei, design the load bearing requirements for
bases according to the service plan.
The load bearing capacity of each base is at least 2 tons.
Assume that each row of cabinets is configured with N bases:
−
If N is less than 5, you can install all the bases at a time. After installation, check
that the total length of each row of bases is the sum of nominal widths of all bases
(tolerance –3 mm to 0 mm).
−
If N is greater than or equal to 5, you are advised to install five bases at a time.
After installation, check that the total length of the bases is the sum of nominal
widths of all bases (tolerance –3 mm to 0 mm). After installing five bases, check
whether the total length of the five bases and the difference between their diagonal
lengths meet the requirements.
If the difference meets the requirements, tighten the bolts and continue to install
next five bases. If the difference does not meet the requirements, adjust the bases to
meet the requirements before tightening the bolts to prevent bases from being
secured in a parallelogram or trapezoid shape.
To ensure accurate locations, you are advised to determine base locations using a laser
locator before installing bases.
|L1–L2| ≤ 5 mm, |L3–L4| ≤ 5 mm