16 (Optional) Installing In-Room Access Control
Devices and Cameras
Issue 02 (2018-03-31)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
251
Figure 16-8
Marking mounting holes
(1) Door frame
(2) Cutout template
(3) Door panel
Step 3
Remove the hoisting strip using the delivered hex key.
Four hex socket screws need to be removed in this step.
Figure 16-9
Removing the hoisting strip
Step 4
Secure the hosting strip using the delivered screws, as shown by (1) in
Pay attention to the direction of the hoisting strip, and ensure that the bulging surface of the
magnetic lock faces the magnet.