FusionModule1000B Water-Cooled IT Solution
Commissioning Guide
7 System Commissioning
Issue 02 (2017-01-10)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
47
Documents:
NetEco Commissioning Guide
,
NetEco Administrator Guide
, monitoring
component layout, initial configuration table of the management system
Skill requirement: weak-current engineer familiar with the management system
For the diagrams and tables, see the initial configuration parameter manual for the solution in use.
The
NetEco Administrator Guide
and
NetEco Commissioning Guide
are integrated in the
iManager
NetEco Product Documentation
.
Procedure
Step 1
Start the management system on the operation terminal. For details, see the
NetEco
Commissioning Guide
.
Step 2
Enter the initial user name and password on the NetEco WebUI to log in to the management
system.
Step 3
Check the connections of all monitoring devices by referring to the monitoring device layout
diagram.
Verify that all devices in the initial configuration table communicate with the management
system properly.
Step 4
Check that the views and videos in the management system are consistent with the running
status of the data center. For details, see
NetEco Commissioning Guide
and
NetEco
Administrator Guide
. If any inconsistency is found, contact Huawei technical support.
----End
7.4 Commissioning the Fire Extinguishing System
(Standard)
Prerequisites
The fire alarm control panel has been powered on.
The management system is working properly.