FusionModule1000A40 Prefabricated All-in-One Data
Center
Installation Guide
9 Installing Cables Outside Pre-fab. Modules
Issue 03 (2020-06-09)
Copyright © Huawei Technologies Co., Ltd.
76
Step 3
Remove the transparent cable protection panel from the power PDB busbar.
Step 4
Route the external input power cables into the power PDB through the cable holes at the
bottom, and route them out along the cable bridge above the cable holes.
Figure 9-2
Connecting input power cables for the power PDB
Step 5
Connect the cables by following the instructions in
A.1 Cable Installation Techniques
After connecting the cables, seal the two cable holes at the bottom of the power PDB using
waterproof sealing putty.
Step 6
Reinstall the transparent cable protection panel, and close the door of the power PDB.
----End
9.2 (Optional) Connecting Generator Start/Stop Cables
(ATS Input)
Prerequisites
Pre-fab. modules and external cable trays have been installed.