FusionModule1000A40 Prefabricated All-in-One Data
Center
Installation Guide
8 Installing Devices Inside Pre-fab. Modules
Issue 03 (2020-06-09)
Copyright © Huawei Technologies Co., Ltd.
53
Step 5
Connect power cables between batteries and reinstall the insulation covers.
Figure 8-3
Place the batteries
(1) Battery
----End
Follow-up Procedure
Verify the battery connections. Ensure that the battery quantity and cable connections comply
with the design and the cables are reliably installed.
8.2 (Optional) Installing the Electric Heating Belt
Prerequisites
The pre-fab. modules have been installed.
Preparations
Tools: None
Materials: low-temperature component suite
Skill requirements: cooling engineer, common technician