Step 2
Route AC output power cables through the protective board at the bottom of the subrack.
Step 3
Secure the AC output power cables to corresponding AC output circuit breakers and
terminals.
Figure 4-13
Installing AC output power cables
(1) AC load
----End
4.10 Installing 220/380 V AC Three-Phase, Four-wire Input
Power Cables
Procedure
Step 1
Route 220/380 V AC three-phase, four-wire input power cables through the protective board
at the bottom of the subrack.
Step 2
Secure the AC input power cables to corresponding AC input circuit breakers and terminals,
as shown in