Figure 5-15
Page of details of a GBTS in the commissioning report (2)
Table 5-10
Page of details of a GBTS in the commissioning report (2)
No.
Description
1
Service verification results of a commissioned GBTS.
2
Automatic fault diagnosis results of a commissioned GBTS.
5.12.4 Parameters of the Performance Counters for GBTS Service
Verification
This section describes the parameters of the performance counters that are monitored in the
service verification procedure during GBTS commissioning.
Parameter Description
Parameter
Description
SDCCH Verification
If the value is not
0
, you can infer that the
counter meets the requirement.
TCH Verification
If the value is not
0
, you can infer that the
counter meets the requirement.
5 Commissioning the MBTS in GL or UL Mode on the
M2000
3900 Series Multi-Mode Base Station
Commissioning Guide
5-50
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Issue 02 (2010-07-30)