5 Installation and commissioning
HSD S.p.A. © - h0104k01a.fm291119
29
5 Installation and commissioning
5.1
Preliminary installation checks
Before carrying out any operations, MAKE SURE:
that no parts of the product have been damaged by impact or any other cause during transport
and/or handling
that the connectors are undamaged
Do not lift the equipment by its electric cables.
5.2
Preparing the factory services
It is the responsibility of the customer to ensure the availability of the factory services (e.g.
electricity supply, compressed air supply, etc.).
The electricity supply line must have a sufficient power rating. The connection to the mains
electricity supply must be carried out by a qualified electrician.
The customer is responsible for the electricity supply to the product, as far as the
connectors.
The user must use a supply connector with a connection to an efficient equipotential
protection circuit.
The earthing system must comply with current standards in the country of
installation and must be checked regularly by qualified personnel.
The product must not be installed in places where there is a risk of explosion.
Installation must be performed in a sufficiently lit area.
5.3
Work environmental requisites
Temperature: from +5 to +40°C (41÷104°F).
Maximum relative humidity (without condensation): 5÷85%.
Maximum altitude: 2000 metres a.s.l. (unless agreed otherwise with the customer).
Standard CEI EN 61800-2.
Summary of Contents for SM 137 D
Page 2: ......
Page 4: ...Information about the publication 4 HSD S p A H5834D0189 fm291119 ...
Page 8: ...Table of contents 8 HSD S p A H5834D0189TOC fm291119 ...
Page 9: ...Preliminaries ...
Page 10: ......
Page 16: ...1 Preliminary information 16 HSD S p A h0101k00a fm291119 ...
Page 20: ...2 Safety information 20 HSD S p A h0115k00a fm291119 ...
Page 21: ...Descriptions ...
Page 22: ......
Page 26: ...3 Main parts 26 HSD S p A h0102k00a fm291119 ...
Page 48: ...5 Installation and commissioning 48 HSD S p A h0104k01a fm291119 ...
Page 49: ...Maintenance ...
Page 50: ......
Page 52: ...6 Maintenance 52 HSD S p A h0107k00a fm291119 ...
Page 53: ...Appendices ...
Page 54: ......
Page 60: ...A Technical characteristics 60 HSD S p A h0124k00a fm291119 ...
Page 62: ...B Disposal 62 HSD S p A h0109k00a fm291119 ...
Page 70: ...Analytical index 70 HSD S p A H5834D0189IX fm291119 ...
Page 71: ......