Removing and replacing the system board
Procedure
Removing the system board
1.
Power down the server (
on page 41).
2.
Remove all power:
a.
Disconnect each power cord from the power source.
b.
Disconnect each power cord from the server.
3.
Remove the server from the rack (
Remove the server from the rack
on page 42).
4.
Remove all power supplies (
Removing and replacing the AC power supply
on page 51).
5.
on page 44).
6.
Do one of the following:
• Remove the air baffle (
on page 52).
• Remove the 4 LFF midplane cage (
Removing and replacing a 4 LFF midplane cage
on page 74).
7.
Remove the primary or secondary PCIe riser cage (
Removing and replacing the primary or
on page 54).
8.
If installed, remove the tertiary PCIe riser cage (
Removing and replacing the tertiary PCIe riser cage
on page 55).
9.
Remove the FlexibleLOM (
Removing and replacing the FlexibleLOM
on page 62).
10.
on page 86).
11.
Do the following:
a.
Observe the guidelines and procedures for NVDIMM relocation (
on
page 90).
a.
Removing and replacing an NVDIMM
on page 87)
12.
Removing and replacing the fan cage
on page 61).
13.
Disconnect all cables connected to the system board.
14.
Observe the following cautions.
CAUTION:
Be sure to loosen each heatsink nut in the order indicated. Otherwise, damage might
occur to the heatsink or processor.
CAUTION:
Install the processor heatsink assembly as soon as possible after removing it. Do not
leave the processor socket unpopulated for extended periods of time.
15.
Remove the processor heatsink assembly:
Removal and replacement procedures
95
Summary of Contents for ProLiant DL388 Gen10
Page 37: ...Customer self repair 37...
Page 38: ...38 Customer self repair...
Page 39: ...Customer self repair 39...
Page 147: ...Option 1 System board Option 2 Controller Option 3 not shown SAS Expander Cabling 147...
Page 149: ...Box 1 to SAS Expander Box 2 to SAS Expander Cabling 149...
Page 151: ...Cable routing Front 8SFF NVMe drive options Box 1 Box 2 Cabling 151...
Page 152: ...Box 3 Cable routing Front 2SFF NVMe drive option for SFF 152 Cabling...