8.
Install the riser cage.
9.
10. Install the server into the rack.
11. Connect the LAN segment cables.
12. Connect each power cord to the server.
13. Connect each power cord to the power source.
The installation is complete.
Installing a 1U or high performance heatsink
This procedure shows a standard heatsink as an example. The installation process is the same for all heatsinks.
Hewlett Packard Enterprise recommends
identifying the processor, heatsink, and socket components before performing
this procedure.
Prerequisites
Before you perform this procedure, make sure that you have the following items available:
• The components included with the hardware option kit
• T-30 Torx screwdriver
• Thermal grease
Hardware options installation
145
Summary of Contents for ProLiant DL380 Gen10
Page 33: ...Component identification 33...
Page 58: ...Operations 58...
Page 124: ...7 Install the rear blank from the option kit Hardware options installation 124...
Page 163: ...Box 1 to SAS Expander Box 2 to SAS Expander Cabling 163...
Page 165: ...Box 1 Box 2 Cabling 165...
Page 167: ...Cable routing Midplane 4LFF drive option Cabling 167...
Page 173: ...Cabling 173...