8/18/2020
HPE FlexFabric 5710 Switch Series - Installing the Switch
3/7
1U chassis rail and long slide rail
Item
Description
1
Chassis rail
2
Long slide rail
top
Rack-mounting procedures at a glance
Follow these guidelines when installing the switch in a 19-inch rack:
1. The distance between the front and rear posts of the rack must meet the below mentioned requirements:
Distance requirements between the front and rear rack posts
Switch model
Installation method
Minimum distancebetween the front andrear
rack posts
Minimum distancebetween the front andrear
rack posts
HPE 5710-
54HF
HPE 5710-
30HF
Using mountingbrackets, chassis rails,and
long slide rails
621 mm (24.45 in)
793 mm (31.22 in)
HPE 5710-54HT
Using mountingbrackets, chassis rails,and
long slide rails
621 mm (24.45 in)
854 mm (33.62 in)
2. To secure the switch to the rack, you must install not only mounting brackets, but also chassisrails and slide rails.
top
Attaching the mounting brackets, chassis rails, andgrounding cable to the chassis
The switch has two mounting bracket installation positions on its two sides: one near the networkport side and one near the power supply
side.
The switch provides a primary grounding point (with a grounding sign) and an auxiliary groundingpoint.
Mounting bracket installation positions and grounding positions on the HPE5710-54HF and HPE 5710-30HF switches