17.
Do one of the following:
• Slide the server into the rack.
•
Install the server into the rack
.
18.
Connect each power cord to the server.
19.
Connect each power cord to the power source.
21. If removed, install the security bezel
.
Installing two M.2 SSDs
For more information about the integrated storage controller and its features, select the relevant user
documentation on the
Hewlett Packard Enterprise website
Procedure
1.
2.
3.
Remove all power:
a.
Disconnect each power cord from the power source.
b.
Disconnect each power cord from the server.
4.
Do one of the following:
•
Extend the server from the rack
•
Remove the server from the rack
.
5.
.
6.
7.
Select the appropriate PCIe slot to install the M.2 SSD enablement board and remove the PCIe blank.
• Slot 1
60
Installing two M.2 SSDs